PLAN: refresh stale Current block; slip MS19 + cascade MS20/MS21
Current block pointed at MS19 Phase 1 (closed); update to Phase 3
active (LLC), Phases 1/2/4 done, 5–8 pending, and refresh the
last-updated stamp.
Slip MS19 end 7/18 -> 8/01 to fit full LLC formation (subsidiary
publication runs into August), and cascade the tail off the old
overlapping windows into clean gaps: MS20 8/03–8/13, MS21 8/15–8/25
(open beta ~2 weeks later). Sync .ics, PLAN targets + release-target
line, and the 19.3 timing note. Local consistency test passes.
Co-Authored-By: Claude Opus 4.8 <noreply@anthropic.com>
- Next action: MS19 Phase 3 — complete LLC formation (parent publication, EINs, business bank account, CryptoZing subsidiary). Phase 5 (Legal Layer) runs as a parallel track.
22
22
- Primary next doc: [`docs/milestones/19_OB_HARDENING_OPS.md`](milestones/19_OB_HARDENING_OPS.md)
23
23
- Most recently completed milestone doc: [`docs/milestones/x18_PRERELEASE_CONTENT_SEO.md`](milestones/x18_PRERELEASE_CONTENT_SEO.md)
24
24
25
25
## Published Release Target
26
-
-**First public release: mid-to-late 2027.** The open beta milestone timeline (MS21, targeting 2026-08-11) covers the open beta. The published release target accounts for post-open-beta work needed before an official first release.
26
+
-**First public release: mid-to-late 2027.** The open beta milestone timeline (MS21, targeting 2026-08-25) covers the open beta. The published release target accounts for post-open-beta work needed before an official first release.
27
27
28
28
## Active and Upcoming Milestones
29
29
| Status | ID | Milestone | Short intent | Target | Primary doc |
|[]| 20 | Mainnet Cutover Preparation | Define and rehearse env flips, wallet validation, mail sanity checks, and backout steps for mainnet cutover. | 2026-07-30|[`docs/milestones/20_MAINNET_CUTOVER_PREP.md`](milestones/20_MAINNET_CUTOVER_PREP.md)|
33
-
|[]| 21 | CryptoZing.app Deployment (Open Beta) | Deploy the open beta under `cryptozing.app`, replace the GitHub Pages placeholder at `/` with the live app landing page without breaking the SEO baseline established in MS15, remove temporary mail aliasing, and complete rollout verification. | 2026-08-11|[`docs/milestones/21_OB_DEPLOYMENT.md`](milestones/21_OB_DEPLOYMENT.md)|
|[]| 20 | Mainnet Cutover Preparation | Define and rehearse env flips, wallet validation, mail sanity checks, and backout steps for mainnet cutover. | 2026-08-13|[`docs/milestones/20_MAINNET_CUTOVER_PREP.md`](milestones/20_MAINNET_CUTOVER_PREP.md)|
33
+
|[]| 21 | CryptoZing.app Deployment (Open Beta) | Deploy the open beta under `cryptozing.app`, replace the GitHub Pages placeholder at `/` with the live app landing page without breaking the SEO baseline established in MS15, remove temporary mail aliasing, and complete rollout verification. | 2026-08-25|[`docs/milestones/21_OB_DEPLOYMENT.md`](milestones/21_OB_DEPLOYMENT.md)|
34
34
35
35
## Completed Milestones
36
36
| Status | ID | Milestone | Short intent | Primary doc |
DESCRIPTION:Deploy the open beta under cryptozing.app, replace GitHub Pages placeholder, remove temporary mail aliasing, complete rollout verification.
Copy file name to clipboardExpand all lines: docs/strategies/19.3_LLC_FORMATION.md
+1-1Lines changed: 1 addition & 1 deletion
Display the source diff
Display the rich diff
Original file line number
Diff line number
Diff line change
@@ -13,7 +13,7 @@ CyberCreek LLC is formed **first**, then CryptoZing LLC is formed **with CyberCr
13
13
14
14
Sequence is serial: CryptoZing's filing can't name CyberCreek as member until CyberCreek exists — which it now does (approved 2026-06-17). CryptoZing's Articles can be filed immediately; AZCC approved CyberCreek in ~9 days, so CryptoZing's approval (the MS21 name-lock) should land well ahead of the swap. CyberCreek's own publication runs in parallel on its 60-day clock (deadline 2026-08-07) and does not gate CryptoZing's filing.
15
15
16
-
**Timing watch-item, not a blocker:**MS21 (deploy-time entity-name swap) is 2026-07-29 (moved out two weeks alongside the rest of MS19 to absorb LLC formation lead time). CryptoZing formation + ~3-week publication now lands ≈7/20, comfortably ahead of the swap. The swap needs the CryptoZing LLC name *locked*— i.e., AZCC Articles approved, which lands early in CryptoZing's window — not the full 3-week publication, which may finish after MS21 as a compliance step. The parallel-track design insulates MS19 regardless: Phase 5 drafts ToS/Privacy with placeholder names, and nothing in MS19 close waits on formation. If AZCC is slow approving CryptoZing's Articles, reconsider then; don't pre-slip.
16
+
**Timing watch-item, not a blocker:**Full LLC formation must land within MS19 (by 2026-08-01); MS21's deploy-time entity-name swap starts 2026-08-15. File the CryptoZing subsidiary now: ~9-day AZCC approval + ~3-week publication lands its formation in early August — within the MS19 window and ahead of the swap. The swap only needs the CryptoZing LLC name *locked*(AZCC Articles approved), which lands well before 8/15; full publication can trail as a compliance step. The parallel-track design insulates MS19 regardless: Phase 5 drafts ToS/Privacy with placeholder names, and nothing in MS19 close waits on formation.