Prepare release 0.35.0 #3251

Open
4 of 45 tasks
Ivansete-status opened this issue Jan 24, 2025 · 1 comment · May be fixed by #3269
Open
4 of 45 tasks

Prepare release 0.35.0 #3251

Ivansete-status opened this issue Jan 24, 2025 · 1 comment · May be fixed by #3269
Assignees
Labels
effort/days Estimated to be completed in a few days, less than a week release Tracks releases

Comments

@Ivansete-status
Copy link
Collaborator

Ivansete-status commented Jan 24, 2025

Items to complete

All items below are to be completed by the owner of the given release.

  • Create release branch

  • Assign release candidate tag to the release branch HEAD. e.g. v0.30.0-rc.0

  • Generate and edit releases notes in CHANGELOG.md

  • Review possible update of config-options

  • End user impact: Summarize impact of changes on Status end users (can be a comment in this issue).

  • Validate release candidate

  • Automated testing

    • Ensures js-waku tests are green against release candidate

    • Ask Vac-QA and Vac-DST to perform available tests against release candidate

      • Vac-QA
      • Vac-DST (we need additional report. see this)
    • On Waku fleets

      • Lock waku.test fleet to release candidate version
      • Continuously stress waku.test fleet for a week (e.g. from wakudev)
      • Search Kibana logs from the previous month (since last release was deployed), for possible crashes or errors in waku.test and waku.sandbox.
        • Most relevant logs are (fleet: "waku.test" OR fleet: "waku.sandbox") AND message: "SIGSEGV"
      • Run release candidate with waku-simulator, ensure that nodes connected to each other
      • Unlock waku.test to resume auto-deployment of latest master commit
    • On Status fleet

      • Deploy release candidate to status.staging
      • Perform sanity check and log results as comments in this issue.
        • Connect 2 instances to status.staging fleet, one in relay mode, the other one in light client.
        • 1:1 Chats with each other
        • Send and receive messages in a community
        • Close one instance, send messages with second instance, reopen first instance and confirm messages sent while offline are retrieved from store
      • Perform checks based end user impact
      • Inform other (Waku and Status) CCs to point their instance to status.staging for a few days. Ping Status colleagues from their Discord server or Status community (not blocking point.)
      • Ask Status-QA to perform sanity checks (as described above) + checks based on end user impact; do specify the version being tested
      • Ask Status-QA or infra to run the automated Status e2e tests against status.staging
      • Get other CCs sign-off: they comment on this PR "used app for a week, no problem", or problem reported, resolved and new RC
      • Get Status-QA sign-off. Ensuring that status.test update will not disturb ongoing activities.
  • Proceed with release

    • Assign a release tag to the same commit that contains the validated release-candidate tag
    • Create GitHub release
    • Deploy the release to DockerHub
    • Announce the release
  • Promote release to fleets.

  • Post release

    • Submit a PR from the release branch to master. Important to commit the PR with "create a merge commit" option.
    • Update waku-org/nwaku-compose with the new release version.
    • Update version in js-waku repo. update only this by submitting a PR.
@Ivansete-status Ivansete-status added the release Tracks releases label Jan 24, 2025
@Ivansete-status Ivansete-status self-assigned this Jan 24, 2025
@Ivansete-status Ivansete-status added the effort/days Estimated to be completed in a few days, less than a week label Jan 24, 2025
@Ivansete-status Ivansete-status moved this to In Progress in Waku Jan 24, 2025
@Ivansete-status
Copy link
Collaborator Author

In this release we are not bumping Status fleets because the recent work won't give a direct impact to them

@Ivansete-status Ivansete-status linked a pull request Jan 31, 2025 that will close this issue
Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment
Labels
effort/days Estimated to be completed in a few days, less than a week release Tracks releases
Projects
Status: In Progress
Development

Successfully merging a pull request may close this issue.