MS19 +2wk for LLC lead time; bind PLAN Target to .ics + guard drift - #98

Merged
n8bar merged 2 commits into
mainfrom
claude/m19-schedule-shift
Jun 10, 2026
Merged

n8bar merged 2 commits into
mainfrom
claude/m19-schedule-shift

Conversation

@n8bar

@n8bar n8bar commented Jun 10, 2026 •

Copy link
Copy Markdown
Owner

What

LLC formation (CyberCreek parent → CryptoZing subsidiary, serial AZCC filing + ~3-week publication each) needs more runway than MS19's original close allowed. This pushes MS19's end out two weeks, slides the downstream milestones, and — to stop the schedule files drifting apart again — binds the two date sources together and guards them.

Schedule shift (+2wk)

MS Was Now
19 05-08 → 07-04 05-08 → 07-18 (start unchanged; underway)
20 07-03 → 07-16 07-17 → 07-30
21 07-15 → 07-28 07-29 → 08-11

Drift fix

The drift's root cause: milestone dates lived in two hand-edited places (milestones.ics and PLAN.md's Target column) with no rule binding them — they'd already diverged ~3 weeks before this change.

  • milestones.ics is the single source of truth. PLAN.md's Target column now equals each milestone's .ics end date (DTEND): MS19 07-18, MS20 07-30, MS21 08-11.
  • MilestoneScheduleConsistencyTest asserts Target == DTEND per milestone. Tagged #[Group('local-only')].
  • Excluded from the PR Tests gate (--exclude-group=local-only) — it runs in the local suite (sail artisan test) so drift fails locally, without gating every PR on a docs invariant.
  • Invariant + mechanism documented in AGENTS.md.

Files

  • docs/milestones.ics, docs/PLAN.md, docs/strategies/19.3_LLC_FORMATION.md
  • tests/Feature/Docs/MilestoneScheduleConsistencyTest.php (new)
  • .github/workflows/pr-tests.yml, AGENTS.md

🤖 Generated with Claude Code

LLC formation (CyberCreek parent → CryptoZing subsidiary, serial AZCC
filing + publication) needs more runway than MS19's original close
allowed. Push MS19 end out two weeks and slide the downstream milestones
to keep the gaps intact.

- MS19: ends 2026-07-04 → 2026-07-18 (start unchanged; underway)
- MS20: 2026-07-03→07-16 becomes 2026-07-17→07-30
- MS21: 2026-07-15→07-28 becomes 2026-07-29→08-11

.ics is canonical; PLAN.md target column shifted +2wk to match. 19.3
watch-item updated to the new MS21 swap date (CryptoZing name-lock ≈7/20
still lands ahead of it). Carries an in-flight 19.3 AFCU edit.

Co-Authored-By: Claude Opus 4.8 <noreply@anthropic.com>

@chatgpt-codex-connector chatgpt-codex-connector Bot left a comment

Copy link
Copy Markdown

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

💡 Codex Review

Here are some automated review suggestions for this pull request.

Reviewed commit: f94002077f

ℹ️ About Codex in GitHub

Your team has set up Codex to review pull requests in this repo. Reviews are triggered when you

  • Open a pull request for review
  • Mark a draft as ready
  • Comment "@codex review".

If Codex has suggestions, it will comment; otherwise it will react with 👍.

Codex can also answer questions or update the PR. Try commenting "@codex address that feedback".

Sequence is serial: CryptoZing's filing can't name CyberCreek as member until CyberCreek exists. Rough path — CyberCreek formation + ~3-week publication (filed 2026-06-08, ≈6/29), then CryptoZing formation + ~3-week publication (≈7/20).

**Timing watch-item, not a blocker:** MS21 (deploy-time entity-name swap) is 2026-07-15. The swap needs the CryptoZing LLC name *locked* — i.e., AZCC Articles approved, which lands early in CryptoZing's window — not the full 3-week publication, which may finish after MS21 as a compliance step. The parallel-track design insulates MS19 regardless: Phase 5 drafts ToS/Privacy with placeholder names, and nothing in MS19 close waits on formation. If AZCC is slow approving CryptoZing's Articles, reconsider then; don't pre-slip.
**Timing watch-item, not a blocker:** MS21 (deploy-time entity-name swap) is 2026-07-29 (moved out two weeks alongside the rest of MS19 to absorb LLC formation lead time). CryptoZing formation + ~3-week publication now lands ≈7/20, comfortably ahead of the swap. The swap needs the CryptoZing LLC name *locked* — i.e., AZCC Articles approved, which lands early in CryptoZing's window — not the full 3-week publication, which may finish after MS21 as a compliance step. The parallel-track design insulates MS19 regardless: Phase 5 drafts ToS/Privacy with placeholder names, and nothing in MS19 close waits on formation. If AZCC is slow approving CryptoZing's Articles, reconsider then; don't pre-slip.

Copy link
Copy Markdown

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

P2 Badge Extend MS19 past the LLC completion date

This updated timing still puts the LLC phase completion after the new MS19 close: the strategy says the serial CyberCreek → CryptoZing formation/publication path lands around 2026-07-20, while the canonical calendar in this commit closes MS19 on 2026-07-18 and the phase exit criteria still require CryptoZing publication to be complete. In that schedule, MS19 can reach its planned close before this required phase can finish, so either the MS19 window needs to move past ≈7/20 or publication needs to be explicitly moved out of MS19 exit criteria.

Useful? React with 👍 / 👎.

Root cause of the drift: milestone dates lived in two hand-edited places
(PLAN.md Target column and milestones.ics) with no rule binding them.

- Reconcile PLAN Targets to the .ics end dates: MS19 2026-07-18,
  MS20 2026-07-30, MS21 2026-08-11 (narrative target updated too).
- Add MilestoneScheduleConsistencyTest asserting PLAN Target == .ics
  DTEND per milestone. Tagged #[Group('local-only')].
- Exclude local-only from the GitHub PR Tests gate; it runs in the
  local suite instead, so drift fails locally without gating every PR.
- Document the invariant + the local-only mechanism in AGENTS.md.

Co-Authored-By: Claude Opus 4.8 <noreply@anthropic.com>
@n8bar n8bar changed the title MS19 +2wk for LLC lead time; slide MS20/MS21 to match MS19 +2wk for LLC lead time; bind PLAN Target to .ics + guard drift Jun 10, 2026
@n8bar
n8bar merged commit 10d84c0 into main Jun 10, 2026
1 check passed
@n8bar
n8bar deleted the claude/m19-schedule-shift branch June 10, 2026 18:07
Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment

Labels

None yet

Projects

None yet

Development

Successfully merging this pull request may close these issues.

1 participant