Sprint 3 achievements, retrospective and Sprint 4 planning notes

Sumit Chachra edited this page Jun 15, 2017 · 5 revisions

High level tasks accomplished

  • Specifications on disaggregations and associated UX issues - #72 https://github.com/unicef/etools-partner-reporting-portal/issues/72
  • Progress report navigation item for IP reporting
  • Most filtering in place now in IP reporting interface
  • More data model changes and associated documentation
  • API for reading indicator data for locations and its structure for disaggregation
  • Be able to view all possible combinations of reported data in the frontend (4 separate components).
  • Begun work (in PR) on data modeling for cluster reporting specific models for projects, objectives etc.
  • Work on mockups for some disaggregation related screens and other misc.

Sprint 4 planning

Tasks available and ready in IP reporting in PRP milestone currently.

Tasks available and ready in Cluster reporting in PRP milestone currently.

Open issues to discuss:

  • Show how we're handling different disaggregation level of reporting per location for same indicator.

Goals are to:

  • Finish API endpoint for user to be able to file a disaggregated data. PUT request. In first 1-2 days of next sprint.
  • Finish work on PD progress report data entry / narrative capture; supporting disaggregated indicator data capture
  • Start work on cluster reporting interface in parallel per project plan.